Dismantling works at HPP Vässinkoski began

June 7, 2017

In May 2017 dismantling of hydraulic units under the project of HPP Vässinkoski upgrading began.

In August 2016 the affiliated company of JSC TYAZHMASH — ČKD Blansko Holding (the Czech Republic) and Fortum Sverige AB signed the contract on repair of Francis turbine.

The generator was successfully dismantled, four shafts were disassembled and shipped to CKD Blansko. The rest dismantled parts will be delivered in two stages at the end of June 2017.