News

Progress of works under “Toachi Pilaton” project (Ecuador)

February 15, 2017

Earlier this month, the second disk pre-turbine gate for Sarapullo HPP was mounted. The first one was mounted in November 2016. Works were accepted by representatives of the Customer.

The third gate for Sarapullo HPP will be completed in March 2017. The affiliated company of JSC TYAZHMASH — ČKD Blansko Holding (the Czech Republic) carries out mounting, supervision installation, and adjustment supervision of disk pre-turbine gates. Under the subcontract agreement, ČKD Blansko Holding will perform mounting of three disk pre-turbine gates for Alluriquin HPP.