Projects Under Construction

In December 2012 the contract on equipment manufacturing for spaceport „Vostochny” was signed between PJSC „TYAZHMASH” and FSUE TsENKI NIISK named after V. P. Barmin.

May 2015

Successful completion of erector testing for Vostochny spaceport.

March 2015

Shipment of launching system major components to the spaceport.

February 2015

Visit of delegation consisting of V. Yu. Vysokikh, Deputy Technical Director of FSUE TsENKI, representatives of FSUE TsENKI NIISK, JSC „Corporation „SPU-TsKB TM”. Purpose of visit: coordination of technical issues and control of erector manufacturing for „Vostochny” spaceport.

January 2015

Launching system packing and preparation for shipment to spaceport.

December 2014

The second stage of testing the launching system for „Vostochny” spaceport.

November 2014

Shipment of maintenance module to spaceport.

September, 2014

Works on maintenance module manufacturing in the workshop No. 6.

Launching system preparation for the first stage of testing.

The first stage of testing the launching system for „Vostochny” spaceport. Significant event not only for „TYAZHMASH” history but also for aerospace industry.

August 2014

Marking the truss in the assembled condition for „Vostochny” spaceport.

June 19, 2014

Technical meeting concerning launching complex units creation for spaceport „Vostochny” was held with representatives of enterprises engaged in the project implementation.

May 2014

Launching system assembly at overpass of the workshop No. 17.

April 2014

Processing the support ring of launching system for „Vostochny” spaceport in the workshop No. 5.

September 2013

Orbiter processing facility of the workshop No. 17 after upgrading.

Completion of caisson for launching system assembly and testing at overpass of the workshop No. 17.

August 2013

Interior finish and insulation of orbiter processing facility of the workshop No. 17.

Concrete casting of caisson foundation.

July 2013

Construction of caisson for launching system assembly and testing at overpass of the workshop No. 17.

June 2013

Improvement of No. 17 workshop overpass, where launching system check assembly and testing will be performed.